Original Request
- Code Version
- 2023
- Code
- EXTBLDG
- Code Description
- Chapter
- 7
- Section
- 707.4
- Topic
- Prevention from Impact Protection > 25%
Question
Does the "25% rule" exemption in 707.4 prevent owners from installing 75% of the glazing WITH impact protection while still allowing them to install 25% without within a 12-month period?
Answer Published 12/12/2025 at 7:35 AM
No, the intent is to allow up to 25% replacement without opening protection in a 12 month period.
Commentary
The code exception specifically indicates "...replaced components does not exceed 25% of the aggregate area of glazed openings..."
The question itself eliminates application of the exception by indicating installation of more than 25%.
NOTE: The intent of this exception is to allow for replacement of items such as a broken or inoperable glazed assembly without imposing the burden of upgrading an existing system.