Interpretation #7881
Published June 12, 2017
Original Request
- Code Version
- 2010
- Code
- BUILDING
- Code Description
- Chapter
- 1
- Section
- 109.2
- Topic
- Schedule of permit fees
Question
Is equipment that falls under the scope of Sections 101.2, 102.2 and 105.1 of the 2010 Florida Building Code, Building, intended to be included in permitting valuations and subject to fees in accordance with the schedule as established by the applicable governing authority pursuant to Section 109.2 of the 2010 Florida Building Code, Building?
Answer Published 06/12/2017 at 3:26 PM
Yes
Commentary
Equipment required for the operation of a facility requires verification of test data, applicable labeling and proper connections. Permit fees pay for the time required to review, inspect and verify this information.