Question
Is it the intent of Section 105.1 to require a separate permit for each structure. Can multiple structures on 1 lot be applied for under 1 permit or is a separate permit required for each structure.
Answer Published 05/09/2013 at 6:34 PM
105.1 does not contain the requirements for the number of
permits required for individual projects. That requirement is
up to the AHJ.
permits required for individual projects. That requirement is
up to the AHJ.