Is it the intent of the FBC-Plumbing code to not
require a cleanout in a horizontal drain after 2
45 degree bends? The line in question has 4-45
degree bends developed over 60 feet fron last
possible rodding point to the exterior cleanout.
Interpretation #7128
Published March 08, 2013
Original Request
- Code Version
- 2010
- Code
- PLUMBING
- Code Description
- Plumbing
- Chapter
- 7
- Section
- 708.3.3
- Topic
- Cleanouts for multiple 45 deg bends
Question
Answer Published 03/08/2013 at 4:44 PM
Per the IPC commentary "The requirement for a cleanout at a
change in direction greater than 45 degrees is for an
individual fitting, not a combination of fittings."
change in direction greater than 45 degrees is for an
individual fitting, not a combination of fittings."