Log in
Edit Distributed Request
Original Request
-
Request ID:
8561
-
Date Submitted:
September 02, 2021
-
Requested By: ayme pappas
-
Code:
Building
-
Edition:
2010
-
Chapter:
1
-
Section:
107.4
-
Topic:
AC Condensate drain line
-
Question:
Does this code apply to where an AC condensate line is changed from the original plan?
-
Comments:
If a line is missed at the underground phase and is run at rough stage through a non bearing wall or is broken under the slab, will an architect or engineer letter be needed to submit for amended plans?
|
|
|