Original Request

  • Request ID: 8504
  • Date Submitted: January 22, 2021
  • Requested By: Dominique Flickinger
  • Code: Energy
  • Edition: 2021
  • Chapter:
  • Section: C408.2.1
  • Topic: Commissioning Plan
  • Question:
    Should the wording for who is to develop the commissioning plan, and therefore conduct the commissioning process, include that the person or approved agency be a 3rd party not affiliated with the design firm or mechanical/electrical engineering firm?
  • Comments:
    The CxP (Commissioning Provider) should be an objective, independent advocate of the Owner. If the CxP's firm has other project responsibilities, or is not under direct contract to the Owner, a conflict of interest will exist. Per USGBC LEED requirements, the CxP should be an independent consultant or a disinterested subcontractor of the design team. The Building Commissioning Association (BCxA) also advocates this; see attached.
  • Attachment 1: Download
  • Use these controls to toggle members of a particular group